Article 06 · Installation · Updated 2026-10-21

Aluminium-Plastic Underfloor Heating: Installation and Acceptance

Eight stages, two pressure-test records and the fields an acceptance form needs before the screed goes in.

Direct answer: a reliable aluminium-plastic underfloor-heating installation is a traceable sequence, not a single gauge reading at the end. Confirm the base, insulation, manifold, circuit labels, spacing, bends, fixing, first pressure test, concealed acceptance, backfill and curing in that order. Before each covering-up step, leave a record that another party can check. Test pressure and hold time must come from the design documents and applicable codes; this page does not invent a site value.

Two installers laying red underfloor-heating pipe in loops on insulation in a room under construction
Laying the loops is only one of eight stages. Acceptance depends on what is recorded before the screed: spacing, bend radius, fixing method and pressure-test data.

Eight stages and what each leaves behind

StageWhat happens on siteWhat goes in the file
1. Base and insulationCheck levelness, lay insulation boards and the reflective layerPhotographs before concealment and a base acceptance record
2. Manifold positioningConfirm height, circuit allocation and service accessCircuit-number schedule matching the labels on the loops
3. Setting out and layingLay to design spacing; add density on cold edges where specifiedMeasured spacing by zone, not a uniform “experience” layout
4. BendingRadius per the grade's technical data; aluminium multilayer holds a set, all-plastic springs back moreMeasured radius and appearance check; whitening, wrinkles or creases mean stop and review
5. Fixing and movementClip or mesh spacing, perimeter insulation, separation joints in large areasPhotographs of the fixing method and spacing
6. First pressure testPressure and hold time per design documents and codesGauge reading, start and end time, ambient temperature, signatories
7. Concealed acceptanceInspect and sign off before backfillingConcealed-works form with loop photographs and matching numbers
8. Backfill and curingProtective layer, strength and moisture control; coordinate the finish sequenceBackfill mix record and curing log

Four site disciplines that prevent rework

No joints in the screed. A joint is almost impossible to inspect after backfilling, so any exception must be agreed and recorded in the project file. Protect the oxygen barrier. Where the outer layer is co-extruded with EVOH, scratches and prolonged outdoor storage weaken the barrier; do not leave an uncoiled pipe exposed to trampling for long. Confirm diameter and turning space at design stage: a pipe that “will not turn” on site usually signals a conflict between diameter, bend radius and build-up thickness, not a careless crew. One pressure test is not enough: keep both the pre-concealment record and the post-backfill re-test.

What the acceptance record must contain

FieldWhy it matters
Circuit number and measured lengthChecks design alignment and underpins pressure-loss and balancing review
Pipe identification: structure, outside diameter × wall, coil length, batchAligns the installed material with samples, shipping documents and test reports
Measured minimum bend radius and appearanceShows whether the aluminium and adhesive layers may have been affected by bending
Test pressure, hold time and pressure dropThe only reviewable acceptance object; values come from design and codes
Environment and backfill conditionBasis for later review of cracking and curing
Photographs and sign-offBasis for responsibility allocation and cross-border claims

Where the supplier fits without replacing site responsibility

A verifiable supply record can identify the pipe structure, outside diameter × wall thickness, coil length and batch, with permanent coil marking and accompanying information. Factory inspection does not certify the installation: workmanship, test parameters and acceptance criteria remain set by the design documents and local requirements. For loop quantities and zoning, see the quantity guide; for the material difference in bending and shape retention, see the STABIL explainer.

Scope and limits

This article is for distributors, installation contractors and project teams aligning site workflow and evidence before concealment. It is not a construction-quality promise or a code conclusion. Requirements vary by country and project, so the design documents, contract annexes and local rules govern. This page deliberately gives no numerical test pressure or hold time.

Sources

Frequently asked questions

Can the final pressure record replace the first test?

No. The pre-concealment test and the post-backfill re-test document different stages and both should be filed.

What bend radius should the crew use?

The minimum bend radius in the technical data for that grade. Do not import a radius from another pipe system or use a generic value without a document.

What pressure and hold time go on the form?

Only the values given by the project design documents and applicable codes. This page intentionally gives no numerical recommendation.

What should happen when a bend is white or wrinkled?

Stop that part of the work, isolate the record and ask the designer or pipe manufacturer for a decision; it should not be accepted on a visual “looks fine”.

← Back to knowledge base Home

Related guides

Wholesale, OEM private-label and distribution — leave your requirement and get a quote within 24 hours.

Email sanlipipe@163.com · WhatsApp +86 150 6880 2744 · video factory audit available

1-minute enquiry, quote within 24 hours

For wholesale, OEM and distribution. Provide either an email or WhatsApp — required.